QA_PROTOCOL_09
STATUS: STAGE_02_VAL

Testing & Validation

Verification matrix for ATLAS system performance. Tracking compliance againstSilver & Gold Tierfunctional requirements.

Validation Coverage
0/12
Global Progress

0%

Active Bench

2

Weight & Alarm System Focus

Critical Blocks

2

Fail-Safe Hardware Gap

Environment

Lab_V1

Controlled Indoor Testing

01

Silver Tier Validation Matrix

Target: Functional Minimum

Cup capacity test (2× 250ml)

Week 7

Place 2 cups filled with 250ml water each on tray. Verify no spillage during normal movement. Tray designed for 1.5–2 kg load capacity.

pending

Total system weight ≤1.5 kg

Week 5

Weigh complete assembled system on scale. Current estimate: 1,331g with PVC + SG90 servos — under target with 169g margin.

in-progress

One-handed & two-handed handling

Week 7

Demonstrate both one-handed hanging carry and two-handed front hold. Verify stability in both modes. Adjust handle positions if needed.

pending

Warning system — multi-level alerts

Week 5–6

Verify all 4 alert levels function: Safe (green LED), Caution (yellow LED + slow beep), Danger (red LED + fast beep), Critical (flashing red + continuous alarm). Firmware written, hardware not yet wired.

in-progress

Battery life ≥6 hours

Week 7–8

Continuous operation test with 2000mAh 7.4V LiPo. Power optimization targets: servo sleep when level, dynamic IMU rate. Estimated ~13 hours with optimizations.

pending

Electronics enclosure — no visible wires

Week 5–6

Verify all wiring routed inside PVC frame. No external connections visible except charging port. Clean, professional appearance.

pending

Tray cleanability — underwater wash

Week 7

Remove tray (magnetic + geometric lock, no tools). Wash underwater. Reassemble and verify waterproof seal. Tray material: acrylic or food-grade plastic.

pending

Fail-safe test — power off → horizontal

Week 5–6

Power off system and verify tray returns to horizontal resting position. Requires torsion springs on both gimbal axes (not yet implemented). CRITICAL GAP.

blocked

Manual lock test — pin lock at horizontal

Week 5–6

Engage manual pin locks on both axes. Verify tray stays level without power or active control. Spring-loaded pins with push-button release. Not yet designed.

blocked
02

Gold Tier Validation Matrix

Target: Enhanced Durability

3-cup capacity test (3× 250ml)

Week 8

Place 3 cups filled with 250ml water. Verify stability with increased load near tray edges.

pending

Splash protection — electronics IP54

Week 8

Spray water on enclosure, verify no electronic damage. Conformal coating on PCB, silicone gasket seals on joints.

pending

Tray swap — 50% larger replacement

Week 8

Replace standard 200mm tray with 300mm tray. Same magnetic mount interface. Test balance and swappability.

pending

Validation Logs Snapshot

Traceability ID: ATLAS_VAL_2026_FEB_15

System Ready for Deployment